Once the required Subcontractors have been added to your job, you can assign them to the appropriate items.

 

Subcontract items can be marked up for enquiry and allocated to items globally. The subcontractors can then be selected for use in the job. The process of global Subcontractor selection is covered later in this manual. This section deals only with the selection of Subcontractors individually, item by item. This will help you to understand the global functions more fully later.

 

Highlight the item in the BoQ Tree that the Subcontractor has priced and click the mouse on the Subcontract tab.

 

If no previous Subcontractor has been assigned, the Subcontractor fields will be empty. The buttons on the top of the Subcontract tab allows you to execute the following functions:

 

Assign a new Subcontractor to the item

Delete a Subcontractor from the item

Use the selected Subcontractor for the item

Do not use the selected Subcontractor for the item


To assign a Subcontractor to the item


1. Click the mouse on the assign a New Subcontractor button. Valesco opens the Add Subcontractor window.



2. Select the required Subcontractor from the Name list of values.

 

3. Check the required radio button for the type of price. This may be a Rate or an Amount (total) for the item.

 

4. Enter the value for the Rate or Amount appropriately. (The unselected radio button will be disabled).

 

The lower field shows the Cost Types set up for this job.



5. Check each appropriate Cost Type check-box that the Subcontractor has NOT priced for this item.

 

6. Check the check-box to accept this Subcontractors price for this item.

 

7. When all the information has been entered click the mouse on the OK button to save the information and close the Add Subcontractor window.