When opening an EVC Template, the resource library can be accessed by either of the two methods below:

 

  • Resource Centre [toolbar – Project or Project Review]
     This popular feature combines the Resource Usage, Resource Assignment & Resource Manager into a single dialogue. The Resource Centre caters for easier editing of Resource & Set Groups.



  • Resource Manager [shortcut CTRL+R]
    This Grid View allows multiple views & resource filters to allow for quick editing and cloning of either Basic or Resource Sets.

     

 

Basic Resources

These are categorised by Cost Type and are the building blocks of the project. Each individual resource is given a Unit of Measure and Base Rate (e.g. Type 1 Aggregate @ £10/T)

 

Resource Sets

This section is the Headings Library, structured by the use of Set Groups.  A Resource Set can be simply a descriptive text, a fully priced composite item, a typical gang build-up, or a combination of all of them.